General Operation And Notes Of Instrument For Building concrete Formwork:
Method of use as well as wooden formwork, hollow plastic concrete Formwork
reinforcement direction with batten direction placed in cross shaped.
No need to smear the mold release agent before using concrete Formwork.
When cast-in-place the flat plate, spacing between the keels should be 20 ~ 25 cm, and the spacing between the wall plate and keels hould be 10 ~ 20 cm.
The seam-line between concrete Formwork should be taped.
The length of nail should not be too long, generally about 30 ~ 35 mm.
The strength to drive nailsshould be moderate.
When removing the concrete Formwork, please start from the small part of one end, the support and the plates should be removed at the same time aiming at preventing the template widespread drops, don't let the corner drop on the ground vertically.
The concrete Formwork accesses to be mixed used with wood veneer, bamboo veneer and other material plate.
pp formwork factory in china